PROJECT DESCRIPTION
Client: Limelight MOB, LLC
Project: New Construction Medical Clinic
General Contractor: Brinkmann Constructors
Floor Area: 21,288 sf
Construction Schedule: April 2017
PROJECT APPROACH
Value Engineering
ROLE
HVAC Mechanical Contractor
PROJECT CHALLENGE/SOLUTION
Wiegmann value engineered the HVAC system, which helped bring the shell and core project within budget.
PROJECT SCOPE
In addition to the main rooftop HVAC system, Wiegmann’s solution included 12 terminal units to provide energy-efficient temporary heating and cooling as tenant spaces are built out.
The two-story Limelight Health Center building, located directly across from Castle Rock Adventist Hospital, will house outpatient therapy clinics for neurology and physical therapy.
“This project was a good success story for a design-assist project. There was good collaboration between the mechanical contractor, general contractor, owner, architect and mechanical engineer of record to bring costs within budget and make the project a success.”